Abstract

This code snippet adds a certain number of days to a date excluding the weekends. By default, when you add a certain number of days to a date the weekends are included. To exclude them, you can use this snippet.

...

Placeholder

Description

Example

<from>Date to which the number of days should be addednew Date()
<nod>Number of days to add22


Examples

The output of this code snippet is a Timestamp which you could use in:

A Groovy expression, for example to:

  • Set a Date/Date-time picker field - Eg: Set a Date-time picker field to 5 days plus the Due date in
    • one of the Set Field Value post-functions
    • the Create issue post-function under Set fields of new issue section

      Code Block
      Date date(Date from, int nod){
          Calendar c1 = GregorianCalendar.getInstance();
          c1.setTime(from);
       
          int weeks = nod/5;
          int remDays = nod%5;
       
          //Adding whole weeks
          c1.add(Calendar.WEEK_OF_YEAR, weeks);
       
          //Run a loop and check each day to skip a weekend
        	for(int i=1;i<=remDays;i++){
            c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
              }
       
          //Skip ending weekend
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
       
          //move to 0:00
          c1.clearTime();
           
          return c1.getTime();
      }
      date(issue.get("duedate"),5)


A Groovy template, for example to:

  • Notify the customer that the issue will be resolved in ten days excluding weekends, through the
    • Comment in one of the Comment issue post-functions
    • Subject/HTML body/Text body of Email issue post-function

      Code Block
      <% Date date(Date from, int nod){
          Calendar c1 = GregorianCalendar.getInstance();
          c1.setTime(from);
       
          int weeks = nod/5;
          int remDays = nod%5;
       
          //Adding whole weeks
          c1.add(Calendar.WEEK_OF_YEAR, weeks);
       
          //Run a loop and check each day to skip a weekend
        	for(int i=1;i<=remDays;i++){
            c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
              }
       
          //Skip ending weekend
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
       
          //move to 0:00
          c1.clearTime();
           
          return c1.getTime();
      }%>