Abstract

This code snippet adds a certain number of days to a date excluding the weekends. Currently, when you add a certain number of days to a date the weekends are included. To exclude them, you can use this snippet.

Logic

  • Fetch the number of days to be added and first add the whole weeks
  • Before adding the remaining days, skip the start if it is a weekend
  • After adding the days, skip the end if it is a weekend
  • Return the Momentjs

Snippet

{% macro add(from, nod) %}
	{% set weeks = nod/5 %}
	{% set weeks = weeks | int %}
	{% set remDays = nod%5 %}

	{# Adding the whole weeks #}
	{% set from = from | date('add', weeks,'weeks') %}

	{# Skipping the weekend if starting with Friday #}
    {% if from | date('day') == "5" and remDays > 0 %}
		{% set from = from | date('add',1,'d') | date %}
	{% endif %}
    
    {# Skipping the starting weekend #}
	{% if from | date('day') == "6" %}
		{% set from = from | date('add',1,'d') %}
	{% endif %}

	{% if from | date('day') == "0"  and remDays == 0 %}
		{% set from = from | date('add',1,'d') %}
	{% endif %}	

	{# Add remaining days #}
	{% set from = from | date('add',remDays,'d') %}

	{# Skipping the ending weekend #}
	{% if from | date('day') == "6" %}
		{% set from = from | date('add',1,'d') %}
	{% endif %}
	{% if from | date('day') == "0" %}
		{% set from = from | date('add',1,'d') %}
	{% endif %}

	{{from | date}}
{% endmacro%}

{% call add(<from>, <nod>) -%}
{%- endcall %}

Placeholders

Placeholder

Description

Example

<from>Date to which the number of days should be addednew Date()
<nod>Number of days to add22

Examples

The output of the code snippet is a Moment.js date object which you could use to:

  • Set a Date/Date-time picker field - Eg: Set the Due date to issue created plus 5 days excluding weekends in
    • one of the Set Field Value post-functions
    • in the Create issue post-function under Set fields of new issue section

      {% macro add(from, nod) %}
      	{% set weeks = nod/5 %}
      	{% set weeks = weeks | int %}
      	{% set remDays = nod%5 %}
      
      	{# Adding the whole weeks #}
      	{% set from = from | date('add', weeks,'weeks') %}
      
      	{# Skipping the weekend if starting with Friday #}
          {% if from | date('day') == "5" and remDays > 0 %}
      		{% set from = from | date('add',1,'d') | date %}
      	{% endif %}
          
          {# Skipping the starting weekend #}
      	{% if from | date('day') == "6" %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}
      
      	{% if from | date('day') == "0"  and remDays == 0 %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}	
      
      	{# Add remaining days #}
      	{% set from = from | date('add',remDays,'d') %}
      
      	{# Skipping the ending weekend #}
      	{% if from | date('day') == "6" %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}
      	{% if from | date('day') == "0" %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}
      
      	{{from | date}}
      {% endmacro%}
      
      {% call add(issue.fields.created, 5) -%}
      {%- endcall %}
  • Notify the customer that the issue will be resolved in 6 days from today through the
    • Comment in one of the Comment issue post-functions
    • Subject/HTML body/Text body of Email issue post-function

      {% macro add(from, nod) %}
      	{% set weeks = nod/5 %}
      	{% set weeks = weeks | int %}
      	{% set remDays = nod%5 %}
      
      	{# Adding the whole weeks #}
      	{% set from = from | date('add', weeks,'weeks') %}
      
      	{# Skipping the weekend if starting with Friday #}
          {% if from | date('day') == "5" and remDays > 0 %}
      		{% set from = from | date('add',1,'d') | date %}
      	{% endif %}
          
          {# Skipping the starting weekend #}
      	{% if from | date('day') == "6" %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}
      
      	{% if from | date('day') == "0"  and remDays == 0 %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}	
      
      	{# Add remaining days #}
      	{% set from = from | date('add',remDays,'d') %}
      
      	{# Skipping the ending weekend #}
      	{% if from | date('day') == "6" %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}
      	{% if from | date('day') == "0" %}
      		{% set from = from | date('add',1,'d') %}
      	{% endif %}
      
      	{{from | date}}
      {% endmacro%}
      
      {% call add(issue.fields.created, 5) -%}
      Your issue will be resolved on/before 
      {%- endcall %}

A Groovy expression, for example to:

Set a Date/Date-time picker field - Eg: Set a Date-time picker field to 5 days plus the Due date in

  • one of the Set Field Value post-functions
  • the Create issue post-function under Set fields of new issue section

date(issue.get("duedate"),5)


A Groovy template, for example to:

  • Notify the customer that the issue will be resolved in ten days excluding weekends, through the
    • Comment in one of the Comment issue post-functions
    • Subject/HTML body/Text body of Email issue post-function

      <% Date date(Date from, int nod){
          Calendar c1 = GregorianCalendar.getInstance();
          c1.setTime(from);
      
          int weeks = nod/5;
          int remDays = nod%5;
      
          //Adding whole weeks
          c1.add(Calendar.WEEK_OF_YEAR, weeks);
      
          //Skipping starting weekend
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
      
          //Add days
          c1.add(Calendar.DAY_OF_MONTH, remDays);
      
          //Skip ending weekend
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
          if (c1.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)
              c1.add(Calendar.DAY_OF_MONTH, 1);
      
          //move to 0:00
          c1.clearTime();
          
          return c1.getTime();
      }
      %>
      Your issue will be resolved on or before <%=date(new Date(),10)%>